Compressor Install

Barnhart was contacted to install two compressors into station housing that was already under construction.

The two generators arrived via the Port of Mobile and were hauled to the site one at a time. Barnhart used two 150-ton cranes to offload the equipment onto sets ofstands and beams at the facility site. Then a six-line Goldhofer PST was positioned under the first piece to lift and transport it to the building site. There, Barnhart had a gantry system set up which lifted the compressor engine off the trailer and then carried it into the building and over the pad, where it was lowered into position.