Facility Expansion

Barnhart was contracted to provide heavy lift cranes to receive and
erect about seven various components in an expansion of the facility.
The fabrication and installation schedule kept changing such that our
scope ultimately was narrowed to receiving and setting the largest two
components, a splitter column and a secondary reactor. The splitter
was erected in March by use of the TC3000 with an Hl-150 tailing.
The secondary reactor was delayed again and the equipment stood
by until late June when the vessel arrived. Again, Barnhart erected the vessel immediately using the TC3000 and the HL-150.